The Malolos – Clark Railway Project (MCRP) is the second section of the Philippine Government’s new railway linking Tutuban in Manila with the International Airport at Clark City Pampanga. CP N-02 consists of the Civil Engineering and Building works for 15.5 km of precast segmental box girder bridge, one extradosed bridge (80m + 140m + 80m), three balanced cantilever bridges (2nos 50m + 70m + 50m and 1no 60m + 100m + 60m), one steel bridge (60m length) and approximately 350m of cast in-situ bridges. The elevated station is situated at the city of San Fernando.
In Cooperation With





May 20, 2024 CP N-02: P-430 to P-433, Sta. 51+750 to Sta. 52+870 Minalin

May 20, 2024 CP N-02: P-460, Sta. 52+815 to Sta. 52+985 BR116, Santo Tomas

May 20, 2024 CP N-02: P-467 to P-470, Sta. 53+225 to Sta. 53+455 BR104, Santo Tomas


April 08, 2024 CP N-02: P-596, Sta. 58+335, San Fernando

April 08, 2024 CP N-02: P-601 to P-605, Sta. 58+520 to Sta. 58+680, San Fernando
Our works
The Malolos – Clark Railway Project (MCRP) is the second section of the Philippine Government’s new railway linking Tutuban in Manila with the International Airport at Clark City Pampanga. CP N-02 consists of the Civil Engineering and Building works for 15.5 km of precast segmental box girder bridge, one extradosed bridge (80m + 140m + 80m), three balanced cantilever bridges (2nos 50m + 70m + 50m and 1no 60m + 100m + 60m), one steel bridge (60m length) and approximately 350m of cast in-situ bridges. The elevated station is situated at the city of San Fernando.
In Cooperation With






After the completion of the steel box girder installation on top of Old San Fernando station the works continues with the preparation for the casting of the concrete slab.
December-2024 CP N-02: BR110 San Fernando

Erection a continuous assembly of the LG2, in San Fernando Station. The second for the total of four Launching Gantries fabricated by ADJV for the erection of the 6182 segments that completes the PSM bridge in the project.
December-2024 CP N-02: LG2 San Fernando Station

The erection of the Steel Box Girder for the 60 m span bridge that will jump on top of the Old San Fernando Station, completed last Friday 13th Dec using 2 crawler cranes of 300 and 600 tons. This operation took approximately 4 hours as the preparation, the trial test and the positioning of the viaduct took place on a heavy congested area around San Fernando station, installing the full piece of the bridge, including bearings in one only step.
13-December-2024 CP N-02: P-597 to P-599 SB, Sta. 58+380 to Sta. 58+440 BR110 San Fernando

The casting sequence for the first Cast-in-Situ (CIS) Bridge in the project has been completed, following a three-step process. CIS 50-9 is a tri-cellular concrete box girder with a full span of 40 meters, designed to accommodate the train line’s central main track and two lateral loops surrounding the platforms at San Fernando Station. The concrete section was cast on a fully supported shoring system. Following this, the process will proceed with the tensioning of the tendons within the concrete section.
13-December-2024 CP N-02: P-595 to P-597, Sta. 58+295 to Sta. 58+380 BR06 (CIS50-9) San Fernando

North-South Commuter Railway Extension (NSCR-EX) Project
The second balance cantilever bridge of the project (BR116) already has the full set composed by 4 form travelers installed up on top of both main piers and starts the cycle of casting of 1 cantilever segment per week.
11-November-2024 CP N-02: P-457 to P-460, Sta. 52+815 to Sta. 52+985 BR116 Santo Tomas

North-South Commuter Railway Extension (NSCR-EX) Project
The steel box girder to be placed on top of the Old San Fernando Station, is nearly completely assembled while more than 7.000 bolts are being tightened on the connections of the 11 segments that composes the bridge.
11-November-2024 CP N-02: P-597 to P-599, Sta. 58+380 to Sta. 58+440 BR110 San Fernando