ADJV site

Our works

We Revolutionize Your Future

The Malolos – Clark Railway Project (MCRP) is the second section of the Philippine Government’s new railway linking Tutuban in Manila with the International Airport at Clark City Pampanga. CP N-02 consists of the Civil Engineering and Building works for 15.5 km of precast segmental box girder bridge, one extradosed bridge (80m + 140m + 80m), three balanced cantilever bridges (2nos 50m + 70m + 50m and 1no 60m + 100m + 60m), one steel bridge (60m length) and approximately 350m of cast in-situ bridges. The elevated station is situated at the city of San Fernando.

In Cooperation With

North-South Commuter Railway Extension (NSCR-EX) Project
Continuous erection of pier head working platform, continuous rebar installation of pier head, pier head works rectification, and on-going cleaning of form panel.

May 20, 2024 CP N-02: P-430 to P-433, Sta. 51+750 to Sta. 52+870 Minalin

North-South Commuter Railway Extension (NSCR-EX) Project
Continuous pre-loading test monitoring, rebar installation at pier table, rebar inspection at pier table, and rebar lifting.

May 20, 2024 CP N-02: P-460, Sta. 52+815 to Sta. 52+985 BR116, Santo Tomas

North-South Commuter Railway Extension (NSCR-EX) Project
Inner form installation (1st stage), installation of post-tensioning ducts, vertical ducts installation for tie rod, cookies for couplers, bolts for turnplate, pre-pour inspection, concrete pouring, applying of curing compound, cutting of strand, group cap installation, formworks cleaning inspection, grinding of installed formworks, and launching of form traveler.
 

May 20, 2024 CP N-02: P-467 to P-470, Sta. 53+225 to Sta. 53+455 BR104, Santo Tomas

North-South Commuter Railway Extension (NSCR-EX) Project
Preparation for segment gluing/stitching, setting of segments to temporary bearing jacks, applying epoxy glue, relocating of dispenser and strand, and relocating of second set of spreader beams .
May 20, 2024 CP N-02: P-502 to P-503, Sta. 54+ 690 to Sta. 54+730, Santo Tomas
North-South Commuter Railway Extension (NSCR-EX) Project
Continuous erection of shoringsupport for access platform and decking of portal.
 
 

April 08, 2024 CP N-02: P-596, Sta. 58+335, San Fernando

North-South Commuter Railway Extension (NSCR-EX) Project
Continuous sheet pile extraction, transfer of sheet pile, removal of waler beams and struts, cutting of weld connection of shet piles.
 
 

April 08, 2024 CP N-02: P-601 to P-605, Sta. 58+520 to Sta. 58+680, San Fernando

Our works

The Malolos – Clark Railway Project (MCRP) is the second section of the Philippine Government’s new railway linking Tutuban in Manila with the International Airport at Clark City Pampanga. CP N-02 consists of the Civil Engineering and Building works for 15.5 km of precast segmental box girder bridge, one extradosed bridge (80m + 140m + 80m), three balanced cantilever bridges (2nos 50m + 70m + 50m and 1no 60m + 100m + 60m), one steel bridge (60m length) and approximately 350m of cast in-situ bridges. The elevated station is situated at the city of San Fernando.

In Cooperation With

North-South Commuter Railway Extension (NSCR-EX) Project

Meanwhile, LG2 at San Fernando Station is advancing with double-shift erection work to rise above the station building.

03-March-2025 CP N-02: P-602 to P-604 CB, Sta. 58+560 to Sta. 58+640 LG2 San Fernando
               

                  


            

North-South Commuter Railway Extension (NSCR-EX) Project

The PSM viaduct erection at the Swampy Area using LG1 has reached Pambaling River, and last month, the gantry crossed the first BC bridge of the N02 project (BR104).

03-March-2025 CP N-02: P-468 to P-469, Sta. 53+295 to Sta. 53+385 LG1 Santo Tomas
                

North-South Commuter Railway Extension (NSCR-EX) Project

Last casting and completion of the backfilling activities on the foundation of San Fernando Station. The most important station on the capital city of Dan Fernando, Pampanga.

17-February-2025 CP N-02: P-601 to P-605, Sta. 58+520 to Sta. 58+680  San Fernando Station

              

               

North-South Commuter Railway Extension (NSCR-EX) Project

Completion of the Second Balance Cantilever Bridge (BR116) of the total of three included on the project. 70m main span bridge that will jump over the DPWH connection road that is still under construction.

17-February-2025 CP N-02: P-457 to P-460, Sta. 52+815 to Sta. 52+985 BR116 Santo Tomas
                

North-South Commuter Railway Extension (NSCR-EX) Project

Segment gluing and stitching, strand threading, and stressing of temporary post-tensioning bars at segment joint.

20-January-2025 CP N-02: P-479 to P-481, Sta. 53+770 to Sta. 53+850 LG1 Santo Tomas
                


               


              

North-South Commuter Railway Extension (NSCR-EX) Project

Continuous transporting and unloading of parapet walls from precast yard to swampy area.

06-January-2025 CP N-02: P-489 to P-493, Sta. 54+170 to Sta. 54+330 Santo Tomas
                


                

Scroll to Top