ADJV site

Our works

We Revolutionize Your Future

The Malolos – Clark Railway Project (MCRP) is the second section of the Philippine Government’s new railway linking Tutuban in Manila with the International Airport at Clark City Pampanga. CP N-02 consists of the Civil Engineering and Building works for 15.5 km of precast segmental box girder bridge, one extradosed bridge (80m + 140m + 80m), three balanced cantilever bridges (2nos 50m + 70m + 50m and 1no 60m + 100m + 60m), one steel bridge (60m length) and approximately 350m of cast in-situ bridges. The elevated station is situated at the city of San Fernando.

In Cooperation With

North-South Commuter Railway Extension (NSCR-EX) Project
Continuous erection of pier head working platform, continuous rebar installation of pier head, pier head works rectification, and on-going cleaning of form panel.

May 20, 2024 CP N-02: P-430 to P-433, Sta. 51+750 to Sta. 52+870 Minalin

North-South Commuter Railway Extension (NSCR-EX) Project
Continuous pre-loading test monitoring, rebar installation at pier table, rebar inspection at pier table, and rebar lifting.

May 20, 2024 CP N-02: P-460, Sta. 52+815 to Sta. 52+985 BR116, Santo Tomas

North-South Commuter Railway Extension (NSCR-EX) Project
Inner form installation (1st stage), installation of post-tensioning ducts, vertical ducts installation for tie rod, cookies for couplers, bolts for turnplate, pre-pour inspection, concrete pouring, applying of curing compound, cutting of strand, group cap installation, formworks cleaning inspection, grinding of installed formworks, and launching of form traveler.
 

May 20, 2024 CP N-02: P-467 to P-470, Sta. 53+225 to Sta. 53+455 BR104, Santo Tomas

North-South Commuter Railway Extension (NSCR-EX) Project
Preparation for segment gluing/stitching, setting of segments to temporary bearing jacks, applying epoxy glue, relocating of dispenser and strand, and relocating of second set of spreader beams .
May 20, 2024 CP N-02: P-502 to P-503, Sta. 54+ 690 to Sta. 54+730, Santo Tomas
North-South Commuter Railway Extension (NSCR-EX) Project
Continuous erection of shoringsupport for access platform and decking of portal.
 
 

April 08, 2024 CP N-02: P-596, Sta. 58+335, San Fernando

North-South Commuter Railway Extension (NSCR-EX) Project
Continuous sheet pile extraction, transfer of sheet pile, removal of waler beams and struts, cutting of weld connection of shet piles.
 
 

April 08, 2024 CP N-02: P-601 to P-605, Sta. 58+520 to Sta. 58+680, San Fernando

Our works

The Malolos – Clark Railway Project (MCRP) is the second section of the Philippine Government’s new railway linking Tutuban in Manila with the International Airport at Clark City Pampanga. CP N-02 consists of the Civil Engineering and Building works for 15.5 km of precast segmental box girder bridge, one extradosed bridge (80m + 140m + 80m), three balanced cantilever bridges (2nos 50m + 70m + 50m and 1no 60m + 100m + 60m), one steel bridge (60m length) and approximately 350m of cast in-situ bridges. The elevated station is situated at the city of San Fernando.

In Cooperation With

North-South Commuter Railway Extension (NSCR-EX) Project

Third process of side shifting from center bound to south bound completed on LG2, and now the erection starts on the last part of the PSM viaduct on San Fernando Station Area will commence in advance to the proposed schedule.

June 2025 CP N-02: P-604 to P-605 CB, Sta. 58+640 to Sta. 58+680 LG2 San Fernando 
               

                  


            

North-South Commuter Railway Extension (NSCR-EX) Project

The construction of main line drainage along the Right of Way progresses at good pace in Zone 2, close to swampy area from piers P-526 to P-510.

June 2025 CP N-02: P-511 to P-515, Sta. 55+040 to Sta. 55+200 Santo Tomas
                

North-South Commuter Railway Extension (NSCR-EX) Project

While LG2 continues with the erection of the South Bound single line segmental bridge in San Fernando Station area.

19-May-2025 CP N-02: P-601 to P-602 NB, Sta. 58+520 to Sta. 58+560 LG2 San Fernando 

              

               

North-South Commuter Railway Extension (NSCR-EX) Project

LG1 has already jumped over the second Balance Cantilever Bridge in Swampy Area (BR116) and started the erection of the 28 pending spans till it reaches the beginning of the project at Pier P-428

19-May-2025 CP N-02: P-455 to P-457, Sta. 52+740 to Sta. 52+81 LG1 Santo Tomas 
                

North-South Commuter Railway Extension (NSCR-EX) Project

Commencement of the activity for the installation of the noise barrier or parapet wall on spans between piers P497-P498 in zone 1 of the project.

April-2025 CP N-02: P-495 to P-498, Sta. 54+410 to Sta. 54+530 Santo Tomas 
                


               


              

North-South Commuter Railway Extension (NSCR-EX) Project

Launching Gantry No. 2 Side shifting, between Center bound viaduct and North Bound of San Fernando Station. Special procedure to complete the works on the station building with the problems on the ROW along San Fernando Area.

April-2025 CP N-02: P-607C-P607NB, Sta. 58+440 to Sta. 58+760 San Fernando 
                


                

Scroll to Top