ADJV site

Our Works – 3rd Quarter 2025

Our works

We Revolutionize Your Future

The Malolos – Clark Railway Project (MCRP) is the second section of the Philippine Government’s new railway linking Tutuban in Manila with the International Airport at Clark City Pampanga. CP N-02 consists of the Civil Engineering and Building works for 15.5 km of precast segmental box girder bridge, one extradosed bridge (80m + 140m + 80m), three balanced cantilever bridges (2nos 50m + 70m + 50m and 1no 60m + 100m + 60m), one steel bridge (60m length) and approximately 350m of cast in-situ bridges. The elevated station is situated at the city of San Fernando.

In Cooperation With

North-South Commuter Railway Extension (NSCR-EX) Project
Continuous erection of pier head working platform, continuous rebar installation of pier head, pier head works rectification, and on-going cleaning of form panel.

May 20, 2024 CP N-02: P-430 to P-433, Sta. 51+750 to Sta. 52+870 Minalin

North-South Commuter Railway Extension (NSCR-EX) Project
Continuous pre-loading test monitoring, rebar installation at pier table, rebar inspection at pier table, and rebar lifting.

May 20, 2024 CP N-02: P-460, Sta. 52+815 to Sta. 52+985 BR116, Santo Tomas

North-South Commuter Railway Extension (NSCR-EX) Project
Inner form installation (1st stage), installation of post-tensioning ducts, vertical ducts installation for tie rod, cookies for couplers, bolts for turnplate, pre-pour inspection, concrete pouring, applying of curing compound, cutting of strand, group cap installation, formworks cleaning inspection, grinding of installed formworks, and launching of form traveler.
 

May 20, 2024 CP N-02: P-467 to P-470, Sta. 53+225 to Sta. 53+455 BR104, Santo Tomas

North-South Commuter Railway Extension (NSCR-EX) Project
Preparation for segment gluing/stitching, setting of segments to temporary bearing jacks, applying epoxy glue, relocating of dispenser and strand, and relocating of second set of spreader beams .
May 20, 2024 CP N-02: P-502 to P-503, Sta. 54+ 690 to Sta. 54+730, Santo Tomas
North-South Commuter Railway Extension (NSCR-EX) Project
Continuous erection of shoringsupport for access platform and decking of portal.
 
 

April 08, 2024 CP N-02: P-596, Sta. 58+335, San Fernando

North-South Commuter Railway Extension (NSCR-EX) Project
Continuous sheet pile extraction, transfer of sheet pile, removal of waler beams and struts, cutting of weld connection of shet piles.
 
 

April 08, 2024 CP N-02: P-601 to P-605, Sta. 58+520 to Sta. 58+680, San Fernando

Our works

We Revolutionize Your Future

The Malolos – Clark Railway Project (MCRP) is the second section of the Philippine Government’s new railway linking Tutuban in Manila with the International Airport at Clark City Pampanga. CP N-02 consists of the Civil Engineering and Building works for 15.5 km of precast segmental box girder bridge, one extradosed bridge (80m + 140m + 80m), three balanced cantilever bridges (2nos 50m + 70m + 50m and 1no 60m + 100m + 60m), one steel bridge (60m length) and approximately 350m of cast in-situ bridges. The elevated station is situated at the city of San Fernando.

In Cooperation With

North-South Commuter Railway Extension (NSCR-EX) Project

LG1 uses the unique method in segment hanging upon crossing the Megildo river, which is the front feeding.  PSM erection at Swampy area is almost done with only 9 spans remaining.

September 2025 CP N-02: P-437 to P-439, Sta. 52+030 to Sta. 52+110 LG1 Minalin
               


            

North-South Commuter Railway Extension (NSCR-EX) Project

Road works of BR105 (Extradosed Bridge) are almost completed. Bored piling works scheduled to commence on the 1st week of October 2025 which begins with sheet piling on each pier.

September 2025 CP N-02: P-660 to P-663, Sta. 60+857.5 to Sta. 61+157.5 BR105-Extradosed Bridge San Fernando
               


                

North-South Commuter Railway Extension (NSCR-EX) Project

At the San Fernando station, the PSM erection 29.14%, parapet wall 126 numbers and secondary column 28.95%

August 2025 CP N-02: P-602 to P-604 NB, Sta. 58+440 to Sta. 58+480 San Fernando Station      

              

North-South Commuter Railway Extension (NSCR-EX) Project

The construction of main line drainage along the Right of Way from piers P-510 to P-526 were completed and erection of the parapet wall will soon start.

August 2025 CP N-02: P-510 to P-526, Sta. 55+005 to Sta. 55+640 Santo Tomas

North-South Commuter Railway Extension (NSCR-EX) Project

For the MCRP 02 team on this month of July, LG2 is continuing making big leap in superstructure side and has two more spans left to be erected – P599 to P600 South Bound. 

July 2025 CP N-02: P-600 to P-601 SB, Sta. 58+480 to Sta. 58+520 San Ferando 
                

North-South Commuter Railway Extension (NSCR-EX) Project

TREVI is commencing with their bored piling activities that start from piers P-609 to P-612. 

July 2025 CP N-O2: P609 to P-612 SB, Sta. 58+840 to Sta. 58+960 San Fernando
                

 
Scroll to Top